Nova Scotia Dykeland System Upgrades Project (DSUP)

Construction Activities to start end of August 2026

The construction is estimated to take approximately 6-8 weeks to complete. 

The truck route will be along Granville Road into town along Route 1 (Evangeline Trail), with a distance of 9 kilometers.

Both tandems and twin steer trucks will be hauling common borrow material and rock to the site;

Hours of Operation during construction:  operation hours will be Monday – Saturday from 7:00 am-7:00 pm.

 

Concerns or Questions?  

Contact:

Pam Davidson, Engagement Lead, DSUP